What Is a Liquidated Damages Clause?
Definition: Specifies a predetermined amount of money that must be paid as damages for failure to perform under a contract.
Also called delay damages, stipulated damages, or (in construction) simply “LDs.”
What this clause actually does
A liquidated damages clause fixes the compensation for a defined failure in advance, so that neither side has to prove actual loss. Common shapes: a daily or weekly rate for late delivery or late completion; a fixed sum per breach of a confidentiality or non-solicitation obligation; a percentage of contract value for early termination; a per-record or per-incident figure.
A well-drafted one is genuinely useful to both sides. You know your maximum exposure; they know what they will recover; nobody litigates about quantum. The problems all come from three specific drafting choices.
The three choices that decide everything
- Is there an aggregate cap? A per-day rate with no total limit runs indefinitely. A long delay can produce a figure larger than the contract itself.
- Is it the sole remedy, or an additional one? “In addition to all other remedies available at law” means you pay the fixed sum and face a damages claim for the same failure. “Sole and exclusive remedy” is the phrase that makes the clause do its job.
- Is it inside the liability cap? If liquidated damages are carved out of the cap, the cap does not limit your largest predictable exposure.
Where it bites
- Delay you did not cause. If the clause does not excuse delay caused by their late approvals, late information, late site or system access, a change order, or a force-majeure event, you are paying for their bottleneck.
- No grace period. Some clauses accrue from the first hour past the date.
- Interaction with “time is of the essence.” Together, these can make a single missed date both a payable sum and a termination trigger.
- Unilateral set-off. A right to deduct the amount from invoices they owe you, without notice and without anyone deciding whether the failure occurred, converts a disputed claim into a cash-flow event.
- Restrictive-covenant versions. A fixed sum per breach of a non-compete or non-solicit can be very large relative to the value of the underlying work, and the trigger is often defined broadly.
- Automatic triggers with no cure right. “Any delay” leaves no room to fix something the same afternoon.
- The clock does not stop. If the rate accrues until acceptance rather than until submission for review, their review time is on your meter.
What to negotiate
- An aggregate cap on total liquidated damages, and a stated relationship to the overall liability cap.
- “Sole and exclusive remedy” for the failure it covers.
- A grace period before the rate starts accruing.
- Day-for-day relief for delay caused by the other party, by a change order, by inputs or approvals they owe you, or by force majeure.
- A mutual equivalent where the delay can run in the other direction — late approvals, late payment, late provision of access.
- Ask how the figure was calculated. A rate that reflects a written estimate of the cost the delay actually causes them is defensible; a round number nobody can explain is worth questioning, and asking the question before signing is worth more than arguing about it afterwards.
- Stepped rates — lower early, higher later — rather than one aggressive flat rate.
- A cure right and a notice requirement before the clause triggers.
- Define when the clock stops — on submission for review, not on completion of their review.
- No unilateral set-off without notice and a short dispute window.
What a reasonable version looks like
A rate tied to a genuine estimate of the cost of the failure; a grace period; automatic day-for-day extension for causes attributable to the other party or to force majeure; an aggregate cap that sits in a stated relationship to the liability cap; status as the sole and exclusive remedy for that failure; a defined stop-the-clock event; and no set-off without notice.
Contract law in many places distinguishes between a figure that represents a genuine attempt to estimate loss and one set primarily to punish, and how a particular number is treated varies by jurisdiction and by how it was arrived at. That is a reason to ask for the reasoning and keep a record of it, and a reason to have a lawyer look at a large figure — not a reason to assume any particular number will or will not stand.
What to push back on hardest
- An uncapped per-day rate.
- A fixed sum “in addition to all other remedies and without proof of loss,” with no cap.
- Liquidated damages plus a termination right plus a general damages claim for the same failure.
- Amounts accruing for delays caused by their own late inputs.
- Liquidated damages expressly carved out of the liability cap.
- Unilateral deduction from your invoices with no notice and no dispute process.
- No pause during a force-majeure event.
Questions worth asking before you sign
- What exactly triggers this, and from what moment?
- What is the rate, and is there a total cap?
- Is it the only remedy for that failure, or an extra one?
- What happens if the delay is caused by you?
- Does force majeure pause it?
- Is it inside the liability cap?
- Can you deduct it from my invoices before anyone agrees I was late?
- How was the figure calculated?
Related clauses
Not legal advice. What's My Contract is not a law firm, and this page is general information about how a clause of this type is usually written — not advice about your contract, and not a statement of the law in any particular place. How a clause is read, and whether it can be relied on, depends on where you are, what the rest of the agreement says, and facts a general explainer cannot know. Before you sign, refuse, or act on any clause, have a lawyer licensed in your jurisdiction read your actual document.
Does your contract have a hidden trap?
Don't rely on generic definitions. Upload your specific PDF and let our autonomous AI find the hidden risks line-by-line.
Scan Contract Now